289 Quarter 2 Performance Report 2022/23 PDF 227 KB
Additional documents:
Minutes:
Members considered the Quarter 2 Performance Report 2022/23 as measured by key projects/activities and key performance indicators (KPIs) set out in the Delivery Plan 2022/23.
The Strategic Advisor (Corporate) provided a brief summary on the report confirming 43 out of 47 KPIs were Green (on track) and 2 Amber (close to target). Two projects had been completed.
The Committee congratulated staff for the second successive quarterly drop in the number of complaints as shown in the report.
With regards to the project ‘Develop full options appraisal for leisure centre provision in Keswick’ members asked when the feasible options and recommendations paper was due out and asked to see a copy once available.
It was agreed to add this as an item for the January OSC meeting.
With regards to the project ‘Carry out feasibility study into provision of BMX track in Workington’ members commented that Cockermouth Town Council received regular requests for a track in the town and asked if they could see a copy of the report for information.
Agreed
That the contents of the report be noted.
243 Quarter 2 Performance Report 2022/23 PDF 227 KB
Additional documents:
Minutes:
The subject of the decision
The Strategic Adviser Performance submitted a report which sought to advise members on the Council’s performance at the end of quarter two 2022/23.
Councillor M Fitzgerald moved the recommendation as per the report; this was seconded by Councillor A Pitcher. The motion was unanimously agreed.
Alternative options considered
None
The reason for the decision
To advise Members of the Council’s performance at the end of quarter two 2022/23.
The decision
Resolved
That the report be noted.